Changelog & Alerts for DCS Versions

Updates between Version 12-2023 and 03-2024

Sections that were updated

File Link File Name Rev. Info Date
Stormwater Management_DC (PDF) Stormwater Management Design Criteria Updated 03/2024
Sustainable Requirements_DC (PDF) Sustainable Requirements Design Criteria Updated 03/2024
UEM Typical P&ID Water Recovery Systems Spec Break Exhibit (PDF) UEM Typical P&ID Water Recovery Systems Spec Break Exhibit New 03/2024
Division 22.UEM - UEM Pipe Specification Tables (XLSX) Division 22.UEM - UEM Pipe Specification Tables Updated 03/2024
22.11.00 (PDF) Facility Water Distribution Updated 03/2024
22.20.00.UEM (PDF) UEM Water Recovery Systems New 03/2024
23.81.26 (PDF) Ductless Split System Air Conditioners New 03/2024
26.05.53 (PDF) Electrical Identification New 03/2024
26.29.13 (PDF) Motor Controllers New 03/2024
Division 33.UEM - UEM Pipe Specification Tables Division 33.UEM - UEM Pipe Specification Tables New 03/2024
33.09.60.3.UEM (PDF) UEM Differential Pressure Transmitter Updated 03/2024
33.14.00.UEM (PDF) UEM Water Utility Distribution New 03/2024
33.61.00.UEM (PDF) UEM Campus Hydronic Energy Distribution Piping and Fittings New 03/2024

Updates between Version 10-2023 and 12-2023

Sections that were updated

File Link File Name Rev. Info Date
Laboratory_DC (PDF) Laboratory Design Criteria New 12/2023
Sustainable Requirements_DC (PDF) Sustainable Requirements Design Criteria New 12/2023
Construction Waste Management_DC (PDF) Construction Waste Management Design Criteria New 12/2023
01.35.23.CIP (PDF) Project Safety Requirements - CIP New 12/2023
01.45.00 (PDF) Project Quality Control New 12/2023
01.77.00.M (DOC) Project Closeout Procedures Deliverable Matrix Updated 12/2023
Division 22 DWS_DC (PDF) Domestic Water Systems Design Criteria Updated 12/2023
22.10.17 (PDF) Natural Gas Piping and Appurtenances Updated 12/2023
22.11.00.UEM (PDF) UEM Facility Water Distribution New 12/2023
22.20.00.23.UEM (XLS) UEM Division 22 Pipe Specification Tables New 12/2023
22.61.19 (PDF) Compressed-Air Equipment for Laboratory and Healthcare Facilities Updated 12/2023
23.07.16.UEM (PDF) UEM Equipment Insulation New 12/2023
23.07.19.UEM (PDF) UEM Piping Insulation New 12/2023
26.28.16 (PDF) Disconnect Switches New 12/2023
32.90.00 (PDF) Landscape Planting Updated 12/2023
33.31.00.UEM (PDF) UEM Site Sanitary Sewerage Piping New 12/2023
33.42.00.UEM (PDF) UEM Site Storm Utility Drainage Piping New 12/2023
33.52.00.UEM (PDF) UEM Site Natural Gas Piping and Appurtenances New 12/2023

Updates between Version 09-2023 and 10-2023

Sections that were updated

File Link File Name Rev. Info Date
01.56.39 (PDF) Tree Preservation, Transplant, and Mitigation Updated 10/2023
01.79.00 (PDF) Demonstration and Training New 10/2023
23.82.13 (PDF) Fan Coil Units New 10/2023
27.51.29.17 (PDF) Emergency Responder Radio Communication Enhancement System New 10/2023

Updates between Version 06-2023 and 09-2023

Sections that were updated

File Link File Name Rev. Info Date
Texas Gas Service Typical P&ID and Natural Gas Spec Break Exhibit Texas Gas Service Typical P&ID and Natural Gas Spec Break Exhibit New 09/2023
UEM Typical P&ID Natural Gas Spec Break Exhibit UEM Typical P&ID Natural Gas Spec Break Exhibit New 09/2023
22.05.23 (PDF) General Valves for Plumbing Piping Updated 09/2023
22.10.17 (PDF) Natural Gas Piping and Appurtenances Updated 09/2023
22.10.17.UEM (PDF) UEM Natural Gas Piping and Appurtenances New 09/2023
22.11.00 (PDF) Facility Water Distribution Updated 09/2023
22.20.00 (PDF) Water Recovery and Rainwater Collection Systems Updated 09/2023
22.30.00 (PDF) Plumbing Equipment Updated 09/2023
22.40.00 (PDF) Plumbing Fixtures Updated 09/2023
22.61.19 (PDF) Compressed Air Systems for Laboratory and Healthcare Facilities Updated 09/2023
23.05.23 (PDF) Valves for HVAC Updated 09/2023
23.21.13 (PDF) Hydronic Piping and Fittings Updated 09/2023
23.22.13 (PDF) Steam and Condensate Piping Updated 09/2023
23.29.00 (PDF) Variable Frequency Drives Updated 09/2023
23.57.00 (PDF) Heat Exchangers Updated 09/2023
23.73.00 (PDF) Indoor Air Handling Units Updated 09/2023
26.05.20 (PDF) 2-Hour Fire-Rated Circuit System New 09/2023
28 46 24.25 (PDF) Area of Refuge Two-Way Communication System New 09/2023

Updates between Version 04-2023 and 06-2023

Sections that were updated

File Link File Name Rev. Info Date
Division 10 Specialties_DC (PDF) Specialties Design Criteria Updated 06/2023
Division 12 Furnishings_DC (PDF) Furnishings Design Criteria Updated 06/2023
08.08.00 (PDF) Commissioning of Openings (Fire Doors, Dampers and Other Opening Protectives) New 06/2023
11.81.29 (PDF) Facility Fall Protection - Active New 06/2023
22.00.00 (PDF) Basic Plumbing Requirements Updated 06/2023
22.62.19 (PDF) Laboratory Vacuum Systems Updated 06/2023
28.00.00 (PDF) Security Updated 06/2023

Updates between Version 03-2023 and 04-2023

Sections that were updated

File Link File Name Rev. Info Date
Fire Alarm_DC (PDF) Fire Alarm Design Criteria Updated 04/2023
10.41.16 (PDF) Emergency Key Cabinets Updated 04/2023
11.81.29 (PDF) Facility Fall Protection - Passive New 04/2023
23.34.00 (PDF) HVAC Fans Updated 04/2023
26.27.26 (PDF) Wiring Devices New 04/2023
28.42.00 (PDF) Gas Detection and Alarm Updated 04/2023
28.46.24.23 (PDF) Other Fire Alarm Interfaces - Building Manager Microphone Updated 04/2023
28.47.00 (PDF) Mass Notification Systems - In-Building Mass Notification Updated 04/2023

Updates between Version 11-2022 and 03-2023

Sections that were updated

File Link File Name Rev. Info Date
Fall Protection_DC (PDF) Fall Protection Design Criteria New 03/2023
Commissioning_DC (PDF) Commissioning Design Criteria New 03/2023
01.91.00 (PDF) Commissioning New 03/2023
26.41.13 (PDF) Lightning Protection for Structures New 03/2023
28.01.80.71 (PDF) Revisions and Upgrades of Fire Detection and Alarm (Modifications of Existing FA Systems) Updated 03/2023
28.46.00 (PDF) Fire Alarm and Signaling (New Systems) Updated 03/2023
32.84.00 (PDF) Planting Irrigation Updated 03/2023

Updates between Version 9-2022 and 11-2022

Sections that were updated

File Link File Name Rev. Info Date
Div 06_WPC_DC (PDF) Woods, Plastics, and Composites Design Criteria New 11/2022
Div 07_Thermal and Moisture Protection_DC (PDF) Thermal and Moisture Protection Design Criteria Updated 11/2022
Div 22_PL_DC (PDF) Plumbing Design Criteria Updated 11/2022
22.05.29 (PDF) Hangers and Supports Updated 11/2022
22.05.53 (PDF) Plumbing Identification Updated 11/2022
22.13.00 (PDF) Facility Sanitary Sewerage Updated 11/2022
22.14.00 (PDF) Facility Storm Drainage Updated 11/2022
22.40.00 (PDF) Plumbing Fixtures Updated 11/2022
22.63.19 (PDF) Laboratory Gas Systems Updated 11/2022
23.22.16 (PDF) Steam and Condensate Specialties New 11/2022
23.22.16.UEM (PDF) UEM Steam and Condensate Specialties New 11/2022
23.25.16.UEM (PDF) UEM Steam and Condensate Flush, Clean, and Passivation New 11/2022
UEM CHW with HEX Typical P&ID and Specification Break Exhibit (PDF) UEM CHW with HEX Typical P&ID and Specification Break Exhibit New 11/2022

Updates between Version 7-2022 and 9-2022

Sections that were updated

File Link File Name Rev. Info Date
Gender Inclusive Campus_DC (PDF) Gender Inclusive Campus Design Criteria New 9/2022
Stormwater Management_DC (PDF) Stormwater Management Design Criteria New 9/2022
UEM Sanitary Sewer Spec Break Exhibit (PDF) UEM Sanitary Sewer Spec Break Exhibit New 9/2022
08.11.13 (PDF) Hollow Metal Doors and Frames New 9/2022
23.05.23.UEM (PDF) UEM Hydronic, Steam, and Condensate Valves New 9/2022
23.20.00.23.UEM (XLSX) UEM Pipe Specification Tables Updated 9/2022
23.22.13.UEM (PDF) UEM Steam and Condensate Piping New 9/2022
23.25.00 (PDF) HVAC Water Treatment New 9/2022
23.74.00 (PDF) Packaged Air Handling Units New 9/2022
26.28.13 (PDF) Fuses, 600Volts New 9/2022
27.41.16 (PDF) Integrated Audio-Video Systems and Equipment New 9/2022
28.01.80.71 (PDF) Revisions and Upgrades of Fire Detection and Alarm (Modification of Existing FA Systems) New 9/2022
28.46.00 (PDF) Fire Alarm and Signaling (New Systems) Updated 9/2022

Updates between Version 6-2022 and 7-2022

Sections that were updated

File Link File Name Rev. Info Date
01.77.00 (PDF) Project Closeout Procedures Updated 7/2022
01.77.00.M (DOC) Project Closeout Procedures Deliverables Matrix Updated 7/2022
Div08_Openings_DC (PDF) Division 08 Openings Design Criteria Updated 7/2022
23.37.00 (PDF) Air Inlets and Outlets New 7/2022
23.51.00 (PDF) Breechings, Chimneys, and Stacks New 7/2022
32.90.00 (PDF) Landscape Planting Updated 7/2022

Updates between Version 5-2022 and 6-2022

Sections that were updated

File Link File Name Rev. Info Date
01.50.00 (PDF) Temporary Facilities and Controls New 6/2022
22.00.00 (PDF) Basic Plumbing Requirements Updated 6/2022
23.05.19.UEM (PDF) UEM Analog Meters and Gauges New 6/2022
23.22.23.UEM (PDF) UEM Steam Condensate Pumps New 6/2022
23.73.00 (PDF) Indoor Air Handling Units Updated 6/2022
26.27.26.UEM (PDF) UEM Wiring Devices Updated 6/2022

Updates between Version 2-2022 and 5-2022

Sections that were updated

File Link File Name Rev. Info Date
07.84.00 (PDF) Firestopping of Penetrations, Joints, and Perimeter Fire Barriers New 5/2022
Div 07_Thermal and Moisture Protection_DC (PDF) Division 07 Thermal and Moisture Protection Design Criteria New 5/2022
11.53.13 (PDF) Laboratory Fume Hoods New 5/2022
22.05.00 Common Work Results for Plumbing Removed 5/2022
22.11.00 (PDF) Facility Water Distribution Updated 5/2022
Div 22_UEM_LWS_DC (PDF) Laboratory Water Service Design Criteria New 5/2022
23.21.23.UEM (PDF) UEM Centrifugal Pumps Updated 5/2022
23.34.00 (PDF) HVAC Fans Updated 5/2022
Div 23_Steam_Systems_DC (PDF) Steam Systems Design Criteria Updated 5/2022
Div 23_UEM_Main Campus_CHWS_DC (PDF) UEM Main Campus Chilled Water Service Design Criteria New 5/2022
Div 23_UEM_Main Campus_District Energy_HHWS_DC (PDF) UEM Main Campus District Energy Heating Hot Water Service Design Criteria New 5/2022
26.05.19 (PDF) Cable Wire and Connectors, 600V New 5/2022
       

Updates between Version 1-2022 and 2-2022

Sections that were updated

File Link File Name Rev. Info Date
01.60.00 (PDF) Product Requirements New 2/2022
23.09.23 (PDF) Direct Digital Control Systems Updated 2/2022
Division 23 Airside Systems Design Criteria (PDF) Division 23 Airside Systems Design Criteria Updated 2/2022
26.00.00 (PDF) Basic Electrical Requirements Updated 2/2022
26.00.10 (PDF) Electrical Demolition New 2/2022

Updates between Version 12-2021 and 1-2022

Sections that were updated

File Link File Name Rev. Info Date
23.22.13 (PDF) Steam and Condensate Piping New 1/2022
26.05.26 (PDF) Grounding New 1/2022

Updates between Version 11-2021 and 12-2021

Sections that were updated

File Link File Name Rev. Info Date
26.51.13 (PDF) Luminaires, Lamps and Poles Updated 12/2021
28.42.00 (PDF) Gas Detection and Alarm New 12/2021
UEM Steam and Steam Condensate Typical P&ID and Spec Break (PDF) UEM Steam and Steam Condensate Typical P&ID and Specification Break Exhibit New 12/2021
UEM CHW WO HX Typical P&ID and Spec Break (PDF) UEM CHW WO HX Typical P&ID and Specification Break Exhibit New 12/2021

Updates between Version 9-2021 and 11-2021

Sections that were updated

File Link File Name Rev. Info Date
Div 01 (PDF) General Requirements Updated 11/2021
01.32.00 (PDF) Construction Progress Documentation New 11/2021
Div22_MGS_DC (PDF) Medical Gas Systems Design Criteria New 11/2021
23.09.13.13.UEM (PDF) UEM Electrical Actuators Updated 11/2021
23.21.13.A.UEM (PDF) UEM Requirements for Water Treatment for Hydrostatic Testing of New Piping Systems Updated 11/2021
23.21.23.UEM (PDF) UEM Centrifugal Pumps Updated 11/2021
27.00.00 (PDF) Communications - System Design, Construction and Commissioning Guide Updated 11/2021
27.05.26 (PDF) Grounding and Bonding for Communications Updated 11/2021
27.05.29 (PDF) Hangers and Supports for Communications Updated 11/2021
27.05.36 (PDF) Cable Trays for Communications Systems Updated 11/2021
27.05.37 (PDF) Firestopping Systems for Communications Cabling Updated 11/2021
27.08.10 (PDF) Optical Fiber Testing and Measurements Updated 11/2021
27.08.20 (PDF) Copper Testing Updated 11/2021
27.11.00 (PDF) Communications Equipment Room Fittings Updated 11/2021
27.11.19 (PDF) Communications Termination Blocks and Patch Panel Updated 11/2021
27.13.23 (PDF) Communications Optical Fiber Backbone Cabling Updated 11/2021
27.15.43 (PDF) Communications Faceplates and Modular Jacks Updated 11/2021
27.51.29 (PDF) Emergency Call Systems Updated 11/2021
33.09.00.UEM (PDF) UEM Meters, Submeters, and Instrumentation for Utilities Updated 11/2021
33.09.60.1.UEM (PDF) UEM Magnetic Flow Meters Updated 11/2021
33.09.60.2.UEM (PDF) UEM Pressure Transmitter Updated 11/2021
33.09.60.3.UEM (PDF) UEM Differential Pressure Transmitter Updated 11/2021
33.09.60.4.UEM (PDF) UEM Temperature Transmitter Updated 11/2021
UT Desirable Tree List UT Desirable Tree List New 11/2021

Updates between Version 8-2021 and 9-2021

Sections that were updated

File Link File Name Rev. Info Date
Codes and Standards (PDF) Codes and Standards Updated 9/2021
01.31.00.CIP (PDF) Project Administration - CIP New 9/2021
01.31.00.Non-CIP (PDF) Project Administration - Non-CIP New 9/2021
10.44.16 (PDF) Portable Fire Extinguishers, Cabinets and Accessories New 9/2021
23.33.33 (PDF) Duct Accessories New 9/2021

Updates between Version 7-2021 and 8-2021

Sections that were updated

File Link File Name Rev. Info Date
Div22_PL_DC (PDF) Plumbing Design Criteria New 8/2021
23 20 00.23.UEM (XLSX) UEM Pipe Specification Tables Updated 8/2021
23 21 13 (XLS) Pipe Specification Tables Removed 8/2021
26.05.33 (PDF) Raceway, Conduit and Boxes New 8/2021
Campus Conditions Campus Conditions Removed 8/2021

Updates between Version 4-2021 and 7-2021

Sections that were updated

File Link File Name Rev. Info Date
23.05.13.UEM (PDF) UEM Motors Updated 7/2021
23.05.53 (PDF) Identification for HVAC Piping and Equipment Updated 7/2021
23.21.13.A.UEM (PDF) UEM Requirements for Water Treatment for Hydrostatic Testing of New Piping Systems Updated 7/2021
23 .21.13.B.UEM (PDF) UEM Procedures for Cleaning, Passivating, & Final Treatment of Chilled & Hot Water Piping Updated 7/2021
Div23_HVAC_SOO_DC (PDF) HVAC Controls Sequences of Operations Design Criteria Updated 7/2021
26.05.43.UEM (PDF) UEM Underground Ducts and Manholes Updated 7/2021
26.13.19.UEM (PDF) UEM 15KV Metal-Clad Switchgear Updated 7/2021
28.00.00 (PDF) Security Updated 7/2021
32.84.00 (PDF) Planting Irrigation Updated 7/2021
33.09.00.UEM (PDF) UEM Meters, Submeters, and Instrumentation for Utilities New 7/2021
33.12.15.UEM (PDF) UEM Direct-Buried Butterfly Valves Updated 7/2021
Standard Operating Procedure for Dye Testing (PDF) Standard Operating Procedure for Dye Testing New 7/2021

Updates between Version 1-2021 and 4-2021

Sections that were updated

File Link File Name Rev. Info Date
01.35.23 (PDF) Project Safety Requirements New 4/2021
Div 09_Finishes_DC (PDF) Division 09 Finishes Design Criteria New 4/2021
09 Finishes 09 Finishes Removed 4/2021
22.05.48 (PDF) Vibration Isolation for Plumbing New 4/2021
22.63.13 (PDF) Medical Gas Systems New 4/2021
23.20.00 (PDF) HVAC Piping and Pumps Updated 4/2021
Div 27_Ext_Elect_Device_DC (PDF) Exterior Electrified Device Design Criteria New 4/2021

Updates between Version 10-2020 and 1-2021

Sections that were updated

File Link File Name Rev. Info Date
01.56.39 (PDF) Tree Preservation and Protection New 1/2021
22.05.13 (PDF) Common Motor Requirements for Plumbing Equipment New 1/2021
22.62.19 (PDF) Laboratory Vacuum Systems New 1/2021
Div 23_CHWS_DC (PDF) Chilled and Hot Water Systems Design Guideline Updated 1/2021
23.05.93 (PDF) Testing, Adjusting and Balancing Updated 1/2021
23.21.23.UEM (PDF) UEM Centrifugal Pumps Updated 1/2021
Main Campus CHW Service Design Specifications (PDF) Main Campus CHW Service Design Specifications Updated 1/2021
Div 26_Electrical_Systems (PDF) Electrical Systems Design Guideline Updated 1/2021
26.05.00 (PDF) Common Work Results for Electrical New 1/2021
26.05.29 (PDF) Hangers and Supports for Electrical Systems New 1/2021
26.05.43.UEM (PDF) UEM Underground Ducts and Manholes Updated 1/2021
26.22.13 (PDF) Low-Voltage Distribution Transformers `New 1/2021
Campus Conditions Campus Conditions Updated 1/2021

Updates between Version 6-2020 and 10-2020

Sections that were updated

File Link File Name Rev. Info Date
22.05.33 (PDF) Heat Tracing for Plumbing Piping New 10/2020
23.21.13.UEM (PDF) UEM Piping and Valves Updated 10/2020
23.21.23.UEM (PDF) UEM Centrifugal Pumps Updated 10/2020
26.00.00 (PDF) Basic Electrical Requirements New 10/2020
26.05.43.UEM (PDF) Underground Ducts and Manholes Updated 10/2020
26.09.23 (PDF) Lighting Control Devices Updated 10/2020
26.24.16 (PDF) Panelboards - Distribution and Branch Circuit New 10/2020

Updates between Version 1-2020 and 6-2020

Sections that were updated

File Link File Name Rev. Info Date
01.57.23 (PDF) Temporary Storm Water Pollution Control Updated 06/2020
01.77.00 (PDF) Project Closeout Procedures New 06/2020
01.77.00M (PDF) Project Closeout Procedures Deliverables Matrix New 06/2020
22.05.29 (PDF) Hangers and Supports New 06/2020
22.11.00 (PDF) Facility Water Distribution Updated 06/2020
22.13.00 (PDF) Facility Sanitary Sewerage Updated 06/2020
23.05.13 (PDF)  Common Motor Requirements for HVAC Equipment New 06/2020
23.21.26 (PDF) Hydronic Specialties New 06/2020

Updates between Version 12-2019 and 1-2020

Sections that were updated

File Link File Name Rev. Info Date
01.57.23 (PDF) Temporary Storm Water Pollution Control New 1/2020
23.09.23 (PDF) Direct Digital Control Systems Updated 1/2020

Updates between Version 10-2019 and 12-2019

Sections that were updated

File Link File Name Rev. Info Date
23.72.00 (PDF) Air-to-Air Energy Recovery Equipment New 12/2019
(PDF)   (DOC)

Energy and Water Performance Information Request

Updated 12/2019

Updates between Version 8-2019 and 10-2019

Sections that were updated

File Link File Name Rev. Info Date
23.05.19 (PDF) Manual Meters and Gauges Updated 10/2019
26.05.73 (PDF)

UEM Standard - Fault and Coordination Study and Arc Flash Hazard Analysis

Updated 10/2019

Updates between Version 5-2019 and 8-2019

Sections that were updated

File Link File Name Rev. Info Date
22.13.19 (PDF) Plumbing Specialties New 09/2019
23.10.00 (PDF) Facility Fuel Systems Updated 09/2019
26.09.23 (PDF) Lighting Control Devices New 09/2019
Link Food Establishment Guidelines New 09/2019
22.11.00 (PDF) Facility Water Distribution Updated 09/2019

Updates between Version 3-2019 and 5-2019:

Sections that were updated:

File Link File Name Rev. Info Date
22.61.19 (PDF) Compressed Air Systems New 05/2019

Updates between Version 2-2019 and 3-2019

Sections that were updated

File Link File Name Rev. Info Date
22.63.19 (PDF) Lab Gas Systems New 04/2019

Updates between Version 11-2018 and 2-2019

Sections that were updated

File Link File Name Rev. Info Date
22.66.00 (PDF) Lab Waste Systems New 02/2019
22.67.13 (PDF) Laboratory and Deionized Water Systems New 02/2019
22.67.13.19 Laboratory and Deionized Water Systems Removed 02/2019

Updates between Version 10-2018 and 11-2018:

Sections that were updated:

File Link File Name Rev. Info Date
Div08_DG (PDF) Division 08 Openings Design Guideline New 11/2018
22.07.19 (PDF) Plumbing Piping Insulation New 11/2018

Updates between Version 9-2018 and 10-2018

Sections that were updated

File Link File Name Rev. Info Date
Div14_CE_DG (PDF) Conveying Equipment Design Guideline New 11/2018
22.13.00 (PDF) Facility Sanitary Sewerage Updated 11/2018
22.14.00 (PDF) Facility Storm Drainage New 11/2018

Updates between Version 8-2018 and 9-2018

Sections that were updated

File Link File Name Rev. Info Date
21.00.00 (PDF) Basic Fire Protection Requirements Updated 10/2018
21.00.10 Standpipe Systems Removed 10/2018
21.05.13 (PDF) Motor Requirements for Fire Suppression Equipment Updated 10/2018
21.05.23 (PDF)  General Valves for Fire Suppression Piping New 10/2018
21.05.29 (PDF) Fire Protection Hangers and Supports New 10/2018
21.05.53 (PDF)  Fire Protection Piping and Equipment New 10/2018
21.10.00 (PDF)  Fire Suppression Systems Updated 10/2018
21.20.00 (PDF) Chemical Fire Extinguishing Systems Updated 10/2018
21.30.00 (PDF)  Fire Pump/Jockey Pump Updated 10/2018
21.40.00 (PDF) UT Jockey Pump Detail Rev. Date Updated  

Updates between Version 6-2018 and 8-2018

Sections that were updated

File Link File Name Rev. Info Date
23.07.00 (PDF) General HVAC Insulation Requirements New 08/2018
23.07.13 (PDF) Ductwork Insulation New 08/2018
23.07.16 (PDF) HVAC Equipment Insulation New 08/2018
23.07.19 (PDF) HVAC Piping Insulation New 08/2018
ITS Room Readiness Checklist ITS Room Readiness Checklist New 08/2018
23.09.23 (PDF) Direct Digital Control Systems Updated 08/2018
HVAC Controls Sequences of Operations Guideline for New Construction and Major Renovations (PDF) HVAC Controls Sequences of Operations Guideline for New Construction and Major Renovations  Updated 08/2018
26.00.00 (PDF) General Electrical Updated 08/2018
23.21.13 (XLS) Pipe Specification Tables Updated 08/2018

Updates between Version 5-2018 and 6-2018

Sections that were updated

File Link File Name Rev. Info Date
23.57.00 (PDF) Heat Exchangers New 07/2018
23.62.00 (PDF) Packaged DX Air Conditioners New 07/2018

Updates between Version 3-2018 and 5-2018

Sections that were updated

File Link File Name Rev. Info Date
23.34.00 (PDF) HVAC Fans Updated 06/2018
23.41.00 (PDF) Particulate Air Filtration New 06/2018

Updates between Version 2-2018 and 3-2018

Sections that were updated

File Link File Name Rev. Info Date
23.29.00 (PDF) Variable Frequency Drives New 03/2018
23.31.00 (PDF) Ductwork Updated 03/2018
26.51.13 (PDF) Luminaires, Lamps and Poles New 03/2018

Updates between Version 12-2017 and 2-2018

Sections that were updated

File Link File Name Rev. Info Date
23.05.93 (PDF) Testing Adjusting and Balancing New 02/2018
23.05.93.13 (PDF) System Preparation for Testing, Adjusting and Balancing New 02/2018

Updates between Version 11-2017 and 12-2017

Sections that were updated

File Link File Name Rev. Info Date
23.36.00 (PDF) Air Terminal Units Updated 12/2017

Updates between Version 10-2017 and 11-2017

Sections that were updated

File Link File Name Rev. Info Date
23.21.13 (PDF) Hydronic Piping and Fittings New 11/2017
Div28_FA_DG (PDF) Fire Alarm Design Guideline Updated 11/2017
Sequences of Operation Guideline (PDF) New   11/2017
Org_Project_Manual (PDF) Organization of Project Manual New 11/2017
Sub_Req_Design_Doc (PDF) Submittal Requirements for Design Documents New 11/2017

Updates between Version 9-2017 and 10-2017

Sections that were updated

File Link File Name Rev. Info Date
23.21.23 (PDF) Hydronic Pumps New 10/2017
28.46.00 (PDF) Fire Alarm and Signaling Updated 10/2017
28.31.90.pdf Emergency Communication System Panel Removed 08/2013

Updates between Version 8-2017 and 9-2017

Sections that were updated

File Link File Name Rev. Info Date
28.39.00 (PDF) In-Building Mass Notification Systems New 09/2017
23.05.23 (PDF) Valves for HVAC New 09/2017
23.05.29 (PDF) Hangers and Supports for HVAC Piping and Equipment New 09/2017

Updates between Version 7-2017 and 8-2017

Sections that were updated

File Link File Name Rev. Info Date
23.73.00 (PDF) Indoor Air Handling Unit New 08/2017
28.00.00 (PDF) Security Updated 08/2017
28.31.63 (PDF) Fire Alarm Integrated Audio Evac Systems - Building Manager Mic New 08/2017
Div_23_Airside_Systems (PDF) Airside Systems Design Guideline New 08/2017
Div_23_Steam_Systems (PDF) Steam Systems Design Guideline New 08/2017
Div_26_Electrical_Systems (PDF) Division 26 Electrical Systems Design Guideline New 08/2017

Updates between Version 6-2017 and 7-2017

*Alert: This updated version of the Design and Construction Standards (version 7-2017) will apply *retroactively* to the Energy Engineering Building project and the Creekside Residence Hall project.

Sections and Divisions that were updated

File Link File Name Rev. Info Date
10.41.16 (PDF) Emergency Key Cabinets New - Added to Division 10 and Division 28 07/2017
22.13.00 (PDF) Facility Sanitary Sewerage Updated 07/2017
23.09.23 (PDF) Direct Digital Control Systems New 07/2017
23.09.43 (PDF) Pneumatic Control System for HVAC Moved/Renamed - Moved from Division 25 to Division 23 07/2017
Div23_CHWS_DG (PDF) Chilled and Hot Water Systems Design Guideline New 07/2017
Division 25 Integrated Automation Removed 07/2017
23.09.00.pdf Instrumentation and Controls for HVAC Removed 07/2017

Updates between Version 4-2017 and 6-2017

Sections that were updated

File Link File Name Rev. Info Date
21.05.13 (PDF) Motor Requirements for Fire Suppression Equipment New 06/2017
22.05.23 (PDF) General Valves for Plumbing Piping New 06/2017
23.00.00 (PDF) Basic HVAC Requirements Updated 06/2017
28.00.00 (PDF) Security Updated 06/2017

Updates between Version 2-2017 and 4-2017

Sections that were updated

File Link File Name Rev. Info Date
Div21_FSS_DG (PDF) Fire Suppression Systems New 04/2017
22.05.53 (PDF) Plumbing Identification New 04/2017
22.10.23 (PDF) Plumbing Pumps New 04/2017
22.20.00 (PDF) Water Recovery Replaced 22 20 03 04/2017
Div22_WRS_DG (PDF) Water Recovery Systems Design Guideline New 04/2017
27.51.29 (PDF) Emergency Call Systems New 04/2017
28.46.00 (PDF) Fire Alarm and Signaling Replaced 28 31 00 04/2017
Div28_FA_DG (PDF) Fire Alarm Design Guideline New 04/2017

Updates between Version 9-2016 and 2-2017

*Alert: This updated version of the Design and Construction Standards (version 2-2017) will apply retroactively to the Energy Engineering Building project and the Creekside Residence Hall project.

The Utilities and Energy Management Standards were added to Divisions 23, 26, and 33.

Sections that were updated

File Link File Title Date
Div22_DWS_DG (PDF) Domestic Water Systems Design Guideline 03/2017
Div22_NGS_DG (PDF) Natural Gas Systems Design Guideline 03/2017
22.00.00 (PDF) Basic Plumbing Requirements 03/2017
22.30.00 (PDF) Plumbing Equipment 03/2017
22.40.00 (PDF) Plumbing Fixtures 03/2017
22.10.17 (PDF) Natural Gas Piping and Appurtenances 03/2017
22.11.00 (PDF) Facility Water Distribution 03/2017
22.30.00.doc Plumbing Equipment 03/2017
22.40.00 (PDF) Plumbing Fixtures 03/2017
27.08.20 (PDF) Copper Testing 03/2017
27.11.00 (PDF) Communications Rooms 03/2017
27.11.13 (PDF) Communications Entrance Protection 03/2017
27.11.19 (PDF) Communications Termination Blocks and Patch Panels 03/2017
27.13.23 (PDF) Communications Optical Fiber Backbone Cabling 03/2017
27.15.13 (PDF) Communications Copper Horizontal Cable 03/2017
27.15.43 (PDF) Communications Faceplates and Modular Jacks 03/2017
27.16.19 (PDF) Telecommunications Patch Cords, Station Cords, and Cross Connect Wires 03/2017
28.00.00 (PDF) Security - General 10/2016